| ID | 188375 |
|---|---|
| Project ID | 63667 |
| Project Step | 2 |
| Project Year | 2569 |
| Step Detail | ดำเนินการก่อสร้างตามแผน ม.ค 69 - มี.ค. 69 |
| Step Percent | 25.00 |
| Step Start | 2026-01-01 00:00:00 |
| Step End | 2026-03-31 00:00:00 |
| Note | (not set) |
| Created At | 2025-12-24 00:00:00 |
| Updated By | 16105 |
| Created By | 16105 |
| Updated At | 2026-04-17 00:00:00 |
| Status Lock | Y |
| Step Sum | (not set) |
| Project Name | (not set) |
| Step Status | 0 |
| Step Reporter | (not set) |
| Project Id1 | (not set) |
| Report Now | 25 |
| Report Note | (not set) |
| Report Date | 2026-04-17 20:46:53 |
| Sed Approved | 1 |
| Sed Approve By | MrHitman |
| Sed Approve At | 2026-01-05 10:55:22 |
| Sed Commentnote | (not set) |
| Subdepart Id Responsible | (not set) |