| ID | 53113 |
|---|---|
| Project ID | 12466 |
| Project Step | 3 |
| Project Year | 2568 |
| Step Detail | ดำเนินการปลูกต้นไม้ในไตรมาสที่ 2 (เดือนมกราคม - มีนาคม 2568) |
| Step Percent | 20.00 |
| Step Start | 0025-01-01 00:00:00 |
| Step End | 0025-03-31 00:00:00 |
| Note | (not set) |
| Created At | 2024-10-27 00:00:00 |
| Updated By | 2340 |
| Created By | 2340 |
| Updated At | 2025-05-11 00:00:00 |
| Status Lock | Y |
| Step Sum | 50.00 |
| Project Name | (not set) |
| Step Status | 0 |
| Step Reporter | (not set) |
| Project Id1 | (not set) |
| Report Now | 20 |
| Report Note | (not set) |
| Report Date | 2025-05-11 12:09:20 |
| Sed Approved | 1 |
| Sed Approve By | 2340 |
| Sed Approve At | 2025-08-25 13:25:03 |
| Sed Commentnote | (not set) |
| Subdepart Id Responsible | (not set) |